21 May 2012

Day 161

Brock and Mark worked on stairs this morning before Brock left for work. The electrician was supposed to be in this afternoon, but I didn't see any evidence of that when I stopped by around 4:30. 

The AC crew was in, and they installed vents in the bedrooms and bathrooms as well as in the exposed duct that runs between the living area and kitchen. The plumber was there with a shipment of toilets, bathroom sinks, and faucets. He installed the dish washer, master bathroom sink faucets, and the disposal in the kitchen sink. 
Master bathroom sinks
Hopefully tomorrow's pictures will be more exciting.